We're sorry, but OSHAcademy doesn't work properly without JavaScript enabled. Please turn on JavaScript or install a browser that supports Javascript.

660 HAZWOPER for General Site Workers I
Skip to main content

HAZWOPER Interactive Scenario

Scene 1: Routine Operations

Read the situation, choose the best response, then review the feedback.

Scenario

It’s 7:30 a.m. You’re in Building 602. Operations include:

  • Heating explosive material in kettles
  • Pouring molten explosives into molds
  • Packaging finished boosters
man pouring into molds

You notice:

  • A slight increase in temperature in one kettle
  • Workers moving quickly to keep production on schedule
  • A faint burnt/chemical odor

Decision Point 1

What do you do?