16-7. Minimum Plan Requirements.
Crane Activity Preparation
- Prior to the start of all crane activities, provide the USACE Contracting Officer (KO) or Contracting Officer's Representative (COR) with detailed crane operation descriptions, qualifications of personnel (operators, riggers, signal persons, lift director), and the Certificate of Compliance (CoC).
Standard Lift Plan (SLP)
- Develop, review, and approve an SLP for each lift, detailing personnel roles, area preparation, lifting equipment (LHE) and load considerations, rigging, and environmental factors. Keep a copy on the LHE and retain for three months.
Standard Lift Plan for Floating Plant
- Supplement the SLP with floating operational parameters, analyze deck loads, adjust rated loads for barges or pontoons, and ensure load charts and operational procedures are accessible on board.
Critical Lift Plan (CLP)
- A critical lift is one that is non-routine, and has specific higher-risk or unusual characteristics (See 16-2) that "trigger" a more detailed Critical Lift Plan (CLP) and additional review/approval requirements. Before any critical lift, a CP or QP must prepare a Critical Lift Plan including detailed lift descriptions, anticipated hazards, site drawings, rigging plans, Load Handling Equipment (LHE) Load Chart, ground and platform conditions, environmental considerations, and lift coordination. The critical lift plan must be submitted to a USACE KO or COR for approval.
Pile Driving Safety Plan
- Develop a site-specific safety plan prior to pile driving, detailing utility locations, equipment operation areas, pile driving sequences, geotechnical reports, daily equipment inspections, and controlled work area plans.
Knowledge Check Choose the best answer for the question.
16-7. What "triggers" a critical lift plan?
You forgot to answer the question!